Asanko Gold Mine Construction Update
2015 1 15 Highlights: Phase 1 construction 24% complete and on schedule for first gold in Q1 2016. Project spend on budget with US$170 million of the US$295 million capital cost committed. Mining contractor mobilized to site and pre stripping of the main Nkran pit underway. Ball and SAG mill concrete foundations poured prior to Christmas contractor shutdown Pit